Owners:Foreign Building Operations (Now Overseas Building Operations) Engineers: Wanchul-Lee & Associates Contractor: Bill Harbert International Construction Inc.
Construction and Schedule Engineer-Managed budgets and schedules for emergency conversion / construction of an eight villa complex to the interim United States Embassy ($7 million). With a ten-day notice to proceed, the project was completed in three months and on-time and under budget. I was responsible for site safety, construction scheduling, contractor correspondence, and AutoCAD as-built drawings.
We were on site surveying the damage days after the bombing. From the actual bombing through the design and construction to the groundbreaking in about six months, our project was completed prior to breaking of ground of the other Embassy rebuild in Kenya which was bombed within seconds of the Tanzanian Embassy.